    Quote Originally Posted by atuter View Post
    This post is written from a General Contractor point of view (like most of my posts anyway):

    All the materials you use on a project will need a formal submittal that needs to be approved by the Architect, Engineers and other consultants as applicable. The making of your submittal log does not start when you start receiving submittals. If this is the case it means you are already late. You should start a submittal log before the project starts, first by going through all your drawings and specifications and determine what submittals are needed. The best way to do is first looking at all the drawings and make a preliminary list of all submittals you can think of, which would be required on this job, as per those drawings. On some projects, Architects or engineers like to make a list of submittals in there too, in addition to specs, so pay attention to the notes too. (You should go through these notes even if there was no special submital section there anyway).

    Once you believe you are finished with going through the drawings, then it is time for a detailed specification review for submittals. All applicable specification section should have a submittal subsection. It is adviseable to go through all of the specifications, not just the submittal section. Remember that the work you are doing at this stage will save you time and effort later. And it definitely will prevent delays and cost impacts on your job. The job you do here will afffect all your submittal tracking process later and it is very important. So be as thorough as you can and if it is possible, show your work to someone else for review. It is always possible to make mistakes on a task which involves so many items. Going through the specification sections will enable you to complete your submittal list. Here remember that on many job, in practice the submittal section is more detailed than needed in actuallity on that job. So, make sure you check with your Architect and Engineer if you have doubts about some sections. Most of the time, they will either waive certain things or make it easier on you for completing the requirements on that submittal as applicable, if it really makes sense for everyone and does not mean cutting any corners or undermining the interest of the Owner. Do not forget that in theory, and by your contract, you owe 100% of those items and requirements listed there to the Owner.

    After you believe you made a complate submittal list, per all the drawings and specifications, now it is time to determine the lead times. Both for the materials themselves, but also the duration for getting the submittal from the subcontractors. Of course you will allow the specified review period for the submittal as well, which is usually 2 weeks. And it is advisable to allow for another round of submittal review, in case the first submittal is not accepted. When you have all these durations, it is time to look at your job schedule and see when you will need that material. Now you can go ahead and mark all these dates counting backwards from the required installation date on your submittal log. This will enable you to track all submittals per your schedule.

    It is strongly recommended that after you determine all the required submittal and material delivery dates, you make a simple table showing all these and get a signed commitment of those dates from each trade. Ideally, when the job was being bought out, the subcontractor signed the contract with a schedule attached. However to make things more clear and as an extra layer of protection for yourself, (as a GC), you should definitely try to get this committed dates signed by your subcontractor. Doing this will i many cases enable them to identify your mistakes or even missing items too. So it is good for everyone actually. It will also make things much smoother between you and your subcontractor through the course of the job because instead of scrabling later and trying to figureout what is needed when later, you are now taking care of everything ahead of time and all needs to be done after that is to follow what was agreed. And since construction is an ideal world where nothing ever goes wrong, things should be juuuust fine... - ok just kidding...

    After you get all the commited dates and finalize your list with your subcontractors input, you should continuously follow up with those items to make sure that everyone is on schedule.

    The things described here will be a headache for you if it is not done properly in the beginning. So treat this step as one of the most important steps of your job and do complete this step as soon as possible, before your job even starts.
    This article was originally published in blog: Making your submittal log and tracking of submittals and materials started by atuter
    Disclaimer: The information in this website is not legal advice and you need to confirm the accuracy of any information yourself, before using it. For your own situation consult a professional. The accuracy of information on this website is not guaranteed. Also, for every situation make sure to take any necessary safety precautions by consulting with a competent construction safety person, before performing any action. By using this site, you agree to these terms. If you do not agree to these terms, do not use this website. Also see forum rules for more terms of use (it is the first thread at the top under "General Discussion" category.)