  • Showing gypsum board (drywall) installation properly - main activity and closing

    In schedules, when showing drywall installation, it is a common mistake to show it as a single item. What precedes drywall are the following: Stud framing, Installation of risers, pipes and conduits, backing or blocking, insulation material. There is an important point however. The drywall does not finish before those pipes and conduits and insulation are done installed. In other words, the predecessors have both SS and FF relationships. This would make the duration of drywall much more than actual. This excessive duration, if you are working with resources will cause inaccurate resource and % complete calculations as well. Here is an example:

    Lets say, Stud framing starts on Day 1.
    At a minimum it must progress a little in order for drywall to start. So lets say, as a predecessor to drywall, we can give a SS+ few days here
    But that is usually not enough. We must also install conduits and pipes and insulation, and they must also progress enough so that we have locations that we can start drywall. So we give another SS + few days predecessors for each of these.

    But then here is the problem… Drywall can not finish, before all these pipes and conduits finish. Starting drywall does not mean we can finish it as we must wait for the completion of these pipes. So what do we do, assign another predecessor with a FF relation this time? No, we can not do that. We can not assign the same activity as two different relations as predecessor. So then what is the solution?

    The solution is, inserting another activity and call it “Close drywall”. This activity will have far less duration that the main drywall installation. But it will take care of that FF relation as predecessor.
    Doing this will also prevent the main drywall activity to be extended excessively and “wait” for those conduits and pipes to finish. This will cause inaccuracies for total work and % complete and resource calculations.
    This article was originally published in forum thread: Showing gypsum board (drywall) installation properly - main activity and closing started by atuter View original post
    Disclaimer: The information in this website is not legal advice and you need to confirm the accuracy of any information yourself, before using it. For your own situation consult a professional. The accuracy of information on this website is not guaranteed. Also, for every situation make sure to take any necessary safety precautions by consulting with a competent construction safety person, before performing any action. By using this site, you agree to these terms. If you do not agree to these terms, do not use this website. Also see forum rules for more terms of use (it is the first thread at the top under "General Discussion" category.)