entering finish no later than constraint to last activity

Home Forums Project Management Project Planning & Control: Costs, Schedules entering finish no later than constraint to last activity

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #215
    atuter
    Keymaster

    When I put a finish no later than constraint to the last activity on my schedule, if it is before its calculated finish date it reduces the total float by 1 day and makes the total float of critical path as -1, which i understand but when i put a finish no later than constraint to that activity after its calculated finish date, nothing changes. why is this not increasing the total float of critical path?