Notification of trades after RFIs

Home Forums Project Management Project Planning & Control: Costs, Schedules Notification of trades after RFIs

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #115
    atuter
    Keymaster

    When there is an RFI you need to make sure that if there is a cost impact, all the necessary parties are notified. They will have to tell you if there is a cost or schedule impact to your project.