Early Start: It means the start date of the remaining work of an activity. This means, before the activity starts, it is equal to start date. But once the activity starts, the start date becomes an actual date, (P6 writes "A" near the date, in start column), and that actual date never changes again, but the early start keeps changing every time you update the schedule and there is still remaining work to be done for that activity.